Industrial unit re-clad without downtime

Aging cladding on a logistics hub refreshed and thermally upgraded while operations continued — no shutdown, no scaffolding circus.

Industrial unit re-clad without downtime — Gatwick, Surrey
Location
Gatwick, Surrey
Property
Commercial · 900 m² warehouse
Area
900 m²
Duration
9 days
Completed
Mar 2025

The challenge

Owners needed a 10-year refresh on tired profile cladding without halting daily HGV movements or the picking operation inside.

Our solution

Phased weekend prep and weekday spray sessions using a charcoal-grey high-build cork system, sealed against driving rain and graffiti-resistant.

Learn about Industrial Spray Coatings

Results

  • Zero operational downtime across the 9-day programme
  • Estimated 22% reduction in summer cooling load
  • Graffiti-resistant top-coat included
  • Branded colour matched to client's livery

"Quietly impressive. They worked around our shifts and the unit looks ten years younger."

Operations Manager · Gatwick logistics client